© National Safe Skies Alliance - Authored by InterVISTAS Consulting
CBP Airport Technical Design Standard
Finding 10: Use Phased FIS Capacity Approach with
Growth Triggers
One of the greatest sources of confusion with the Airport Technical Design Standards is the set of tables used to
calculate baseline space allocation. In the 2016 update to the ATDS, CBP has indicated that there is:
a) flexibility to the baseline space requirements; and
b) a process through the CBP Field Operations Facilities Program Management Office Project Manager (FOF PMO
PM) to allow exemptions from the ATDS.
Airport Applicability
- Small to medium passenger volumes
- All airport types
- All passengers types
References
ATDS (2012)
- Section 2.7.4 states that the FIS must
accommodate all arriving passengers and
queues at peak times
- Section 3.1 introduces the airport size
specification
ATDS (2016 - 90% Draft)
- Section 2.7 states that the FIS size is
determined by passengers arriving at peak
hours plus the size of aircraft which arrive
- Section 5.3 outlines the space matrix and
calculations required for the FIS
- Code ATD-01-03 in Chapter 5
Finding 10: Use A Phased FIS Capacity Approach with
Growth Triggers
In the ATDS, the set of tables used to calculate baseline space allocation has caused some confusion.
In the 2016 update to the ATDS, CBP has indicated that there is:
a) Flexibility to the baseline space requirements
b) A process through the CBP Field Operations Facilities Program Management Office Project Manager to allow
exemptions from the ATDS.
The series of triggers and phases provides
flexibility for an airport to expand when
growth warrants it, not by fixed calendar
dates. All of this should be tied to both the
physical processing capacity (passengers per
hour) from a spatial and processor (e.g. kiosk,
other automation) solution.
Manage risks: For example after
approximately 12 years within an existing
facility, demand growth may be slower than
anticipated. Phased capacity expansion may
be built to accommodate the increased
number of passengers up until a trigger point
is reached. The airport may then proceed to
execute construction for phase 2 capacity
expansion in order to meet demand only when
and if it is needed.
Delivery of facilities could be done with shell
space as quickly as one year, or for larger
projects 2-3 years. The amount of flexible
space could ensure that the timing of capital
and operations are not out-of-sync and meet
demand appropriately.